Section 4

4. PROPOSED TIMING

Following the appointment by AREXPO of an Advisor, whose first task is to develop a Master Plan for the former EXPO area, the Work Team will provide the Advisor with a project for the two Parks (which however is already known to AREXPO), together with an implementation timing.
Table VII reports a preliminary timing.
The plan will develop through 8 semesters, the first one being devoted to the completion of the feasibility study and the following seven to the design and implementation, startup and coming on stream of both Parks.
One separate project (the Mainland Territory) will be devoted to the network of biking paths, especially those under completion, connecting the Mainland with the city of Milan.

 Table VII